BENGALURU, Nov. 27, 2026 — Kempegowda International Airport began letting aircraft take off at the same time from both of its parallel runways on Nov. 27. The change could raise the airport’s hourly capacity by about 42%. Meanwhile, roadworks on the main road to the airport are expected to last about 18 months.
What happened
Until now, Bengaluru’s two parallel runways have been used separately, one for arrivals and one for departures. From Nov. 27, the airport is bringing in simultaneous runway operations. This means departures can be cleared from both runways at the same time, subject to air traffic control clearance and safety requirements, Asianet Newsable reported. Bengaluru is the second Indian airport after Delhi to work this way.
India’s aviation regulator, the DGCA, approved the airport operator’s proposal for this “mixed-mode” use of the runways on Nov. 3. A trial was held on Nov. 20. Between noon and 1 p.m. the airport handled about 40 departures and 20 arrivals. The first simultaneous departures, an IndiGo flight to Mangaluru and an Air India Express flight to Goa, left from the northern and southern runways at about 12:20 p.m.
| Item | Detail |
|---|---|
| Start date | Nov. 27, 2026 |
| Regulator approval | DGCA, Nov. 3, 2026 |
| Approved capacity before | About 60 movements an hour (30 arrivals, 30 departures) |
| Expected capacity | About 85 movements an hour, roughly 42% more |
| Airport road works | About 18 months from Nov. 6, 2026 (exact end date: TBA) |
The airport operator is also building more taxiways and aircraft parking bays and has a western cross-taxiway planned. Terminal 2 is being expanded and a new control tower is under way. Asianet noted that the real gains will depend on weather, airspace restrictions, traffic levels and ground handling.
Getting to the airport
Curly Tales, citing the Hindustan Times, reported that traffic on the road to the airport will be affected for about 18 months from Nov. 6. The cause is the Bengaluru Development Authority’s construction of a four-lane elevated corridor on Ballari Road between UAS Staff Quarters and Mekhri Circle. KSRTC and private buses and all goods vehicles are barred from that stretch. Drivers coming from Hebbal, emergency vehicles included, are being told to use other routes. Suggested detours run via Old High Grounds Junction, Kalpana Junction, Old Udaya TV Junction, Cantonment Railway Station, Tannery Road and Nagawara Road. From Yeshwanthpur, the suggested route is via Mattikere Road, BEL Circle and the Ring Road.
What it means for non-revs
- Possibly fewer departure holds. If both runways can send aircraft out at once, peak-hour queues for take-off should be shorter. That helps tight connections in and out of BLR. How much it helps depends on traffic and weather.
- Extra capacity does not mean extra seats yet. The runways can now handle more flights, but loads only improve if airlines add flights. Watch for new schedules rather than expecting more open seats straight away.
- Leave more time for the road. The real risk to making your flight may be getting to the airport. Buses are barred from part of Ballari Road and detours are in place, so leave early.
- Construction continues. Taxiway, apron and Terminal 2 works mean the layout on the ground can change. Check your terminal and gate before you go.
Sources
- Asianet Newsable — Bengaluru Airport’s New Runway System From November 27: Will Flight Delays Reduce?
- Free Press Journal — Bengaluru Airport Gets DGCA Nod For Mixed-Mode Runway Operations
- Curly Tales — Bengaluru Airport Gets 42% Flight Capacity Boost, But Travellers Face 18 Months Of Road Disruptions